Mineral Resources Limited acquired all the assets of Empire Oil & Gas NL in 2017 after the company and its subsidiaries entered voluntary administration early that year.
The Red Gully Gas and Processing Facility was the first dedicated gas and condensate rich processing facility constructed in the Onshore Perth Basin. It treats the Gingin West-1 and Red Gully-1 gas and condensate to the specification required for entry into the Dampier to Bunbury Natural Gas Pipeline and the BP Kwinana Refinery.
The Red Gully Gas and Condensate Processing Facility is located near Gingin Western Australia. The processing facility consists of the development of two on-shore wells, Gingin West-1 and Red Gully-1, which feed gas and condensate through a processing facility that produces 8 terajoules/day of natural gas and 400bbl/day of condensate.
With a pedigree in hydrocarbon facility, pipeline design and construction and zero recorded injuries.
SCOPE
- Construct civil works.
- Detail, fabricate, deliver and install over 2,500m of piping.
- Install gas processing equipment.
- Install electrical equipment and 25km of electrical reticulation.
- Maintain compliance to required hazardous area classification.
Primero proudly delivered the works within budget, schedule, and over 50,000 man-hours injury free. From an operational readiness perspective, Primero developed the commissioning plan and completions procedures required for start-up and handover of the plant.