OPF2 Vertical WHIMS Plant

Client
Category

Location
Commodity

FMG
Iron Ore
Christmas Creek, Western Australia
Iron Ore
WHIMS IMAGE scaled OPF2 Vertical WHIMS Plant 1

Primero was engaged by Fortescue Metals Group (FMG) to implement a process plant upgrade at its Christmas Creek mine, located in Western Australia’s Pilbara, after having successfully completed an ECI phase.

In under 12 months, we successfully delivered our lump sum design and construct model thanks to close collaboration with FMG, which has subsequently paved the way for further ongoing works with FMG at its Queens and Eliwana projects.

SCOPE

Utilising Vertical Wet High Intensity Magnetic Separation (V-WHIMS) technology, the upgrade was to enable the increased recovery of saleable fine material processed in the Desands unit at the Christmas Creek Ore Process Facility #2 (OPF2).

Responsible for the design, supply, construction and commission of a new Vertical WHIMS facility, scope of works included:

  • Tie-in and pipe routing from scrubbing and wet screening circuit to new guard screen bank.
  • Feed guard screens to magnetic circuit.
  • Agitated feed storage tank.
  • Magnetic drum separation (MOS).
  • Transport of tailings from magnetic circuit tailing hoppers.
  • Slurry transport of magnetic concentrate to new thickener.
  • Installation of belt filters.
  • Provision of services to meet the V-WHIMS circuit demand, including process water, raw water, gland water, potable water, fire water, instrument air, and plant air.
  • Provision of LV switch rooms, electrical equipment and electrical reticulation.
  • Installation of communication and control systems equipment.
  • Brownfield tie-in works.